Bryant Neighborhood Playground Renovation
Updated: November 19, 2025
Updated: March 4, 2026
Early 2026
Seattle Parks and Recreation (SPR) is happy to announce Bryant Playground Park is open! This construction package includes play area improvements at Ward Springs Play Area, View Ridge Playfield Play Area and Bryant Playground Park.
Please watch this site for a ribbon cutting celebration in June 2026.
View the final play equipment renderings below!
Location
Bryant Neighborhood Playground: 4103 NE 65th St, Seattle 98115
Budget
Seattle Park District provides $1,098,000 for planning, design, and construction.
Schedule
Planning: 2023
Design: 2024 - Spring 2025
Construction: Late Fall 2025 - Early 2026
Project Description
This project replaced the existing play area and made accessibility improvements. All improvements will meet accessibility requirements.
Community Participation
Thank you to everyone who joined us during the community engagement phase. We value your feedback and participation. Please follow this page for construction and completion updates.
Public Meeting - 4/10/24
Open House - 10/18/23
Location
Bryant Neighborhood Playground: 4103 NE 65th St, Seattle 98115
Budget
Seattle Park District provides $1,098,000 for planning, design, and construction.
Schedule
Planning: 2023
Design: 2024 - Spring 2025
Construction: Late Fall 2025 - Early 2026
This project is part of a package of three play areas that are being renovated. The above planned construction duration includes renovations at all three locations.
Project Description
This project will replace the existing play area and make accessibility improvements. All improvements will meet accessibility requirements.
The play area will be closed throughout construction.
Community Participation
Thank you to everyone who joined us during the community engagement phase. We value your feedback and participation. Please follow this page for construction and completion updates.
Public Meeting - 4/10/24
Open House - 10/18/23